What to Expect

Phase 1

Early Works
Late Summer 2022 – Early 2023

  • Construct the Harmon Channel concrete drainage box culvert to accommodate the future widening of I-15
  • Drainage and utility work

Lane restrictions:

  • Dean Martin north of Tropicana
  • Tropicana between Dean Martin and Polaris
Click to Enlarge

Phase 2

Tropicana Northside
Early 2023 – Winter 2023

  • Demolition of the north half of the Tropicana bridge over I-15 and Frank Sinatra Drive
  • Construction of the Tropicana Bridge over Dean Martin Drive
  • Partial reconstruction of the southbound I-15 to eastbound Tropicana Avenue flyover bridge

Lane Restrictions:

  • I-15 NB and SB
  • Tropicana and ramps
  • Frank Sinatra
Click to Enlarge

Phase 3

Tropicana Southside
February 2024 – Fall 2024

Improvements to the south side of Tropicana Avenue in preparation for the reopening of the I-15/Tropicana flyover

Demolition of the south half of the Tropicana bridge over I-15 and Frank Sinatra Drive

Reconstruction of bridges over I-15, Frank Sinatra and Dean Martin Drive

Click to Enlarge

Phase 4

Dean Martin Dr
Late 2024 – Summer 2025

Dean Martin Dr connection under Tropicana

Lane Restrictions:

  • Dean Martin
Click to Enlarge