“DROPICANA” Demolition Event Kicks Off Phase 2

NDOT is preparing to start Phase 2 of the I-15 Tropicana interchange project. The most impactful portion of Phase 2 will be an 8-day demolition event that will include the demolition of two bridges, the I-15 SB flyover ramp to Tropicana eastbound and the Tropicana bridge over I-15. These demos will result in closures of Tropicana, the I-15 ramps that access Tropicana, and a closure of I-15 itself for two days.

Starting 1/17 at 9pm: I-15 SB ramp access to Tropicana Ave CLOSED

Starting 1/22 at 11pm: Tropicana Ave over I-15 CLOSED. All I-15 ramp access to and from Tropicana Ave CLOSED.

1/27 at 10pm until 1/30 at 5am: I-15 NB & SB CLOSED between Flamingo and Russell.

NDOT works closely with the free app Waze – which can give you the fastest route to your destination during these closures. Plan for extra commute time and please drive safely. Learn more!